Seminar Registrations

Construction & Surety Lawyers • Mediators • Arbitrators


CGS Home
Lawyer Profiles
Practice Details
Contact Us
Maps & Directions
Programs & Events
CGS Publications
Construction Law Notes
Construction Links
Employment
Disclaimer
Privacy Policy
Conner Gwyn Schenck PLLC © 2000. All rights reserved.

 

NORTH CAROLINA CONSTRUCTION LIEN HANDBOOK

INTRODUCTION

This Handbook and all forms and agreements herein are designed and intended to provide general information to contractors, subcontractors and others about the requirements of the North Carolina lien statutes. Nothing in this Handbook is to be considered as the rendering of legal advice for specific cases. Although this Handbook was written by professionals, it should not be used as a substitute for consultation with an experienced attorney. If legal or other professional advice is required, the services of a professional should be sought.

TABLE OF CONTENTS

 

I. Contractor's Lien

 

A. Basic requirements

 

1. What does it mean to have a contract with the owner of real property?

 

2. What does it mean to improve the real property?

 

B. Effective date of the lien

 

C. Perfecting and enforcing a lien

 

1. Contents of the Claim of Lien

 

2. Time for filing

 

3. Amendment of the Claim of Lien

 

4. Time for enforcing the Claim of Lien

 

D. Discharging and waiving a lien

 

II. Subcontractor's Liens

 

A. Lien on funds

 

1. Funds subject to the lien on funds

 

2. Perfecting and enforcing a lien on funds

 

a. Contents of the Notice of Claim of Lien

 

b. Obligor's responsibility upon receipt of Notice of Claim of Lien

 

c. Enforcing the lien on funds

 

3. Discharging a lien on funds

 

B. Lien on real property

 

1. Contents of the Claim of Lien

 

2. Time limits

 

C. Special defenses to subcontractor liens on real property Notice of Contract

 

III. Forms

 

A. Notice of Claim of Lien By First Tier Subcontractor

 

B. Notice of Claim of Lien By Second Tier Subcontractor

 

C. Notice of Claim of Lien By Third Tier Subcontractor

 

D. Notice of Claim of Lien By Subcontractor More Remote Than The Third Tier

 

E. Notice of Contract

 

F. Notice of Subcontract

 

G. Claim of Lien

 

H. Lien Checklist

PREFACE

A mechanic's lien is a special legal right and remedy for parties who contribute labor, materials, rental equipment or services to improve real property. The lien may entitle the person who holds the lien to force the sale of the improved real property to pay for the improvement. In North Carolina, there are different lien rights and procedures depending upon whether the claimant has a contract directly with the owner of the improved real property or a contract with someone other than the owner. In this Handbook, the term "contractor" means any proper lien claimant who has a contract directly with the owner of the improved real property. The term "subcontractor" means any proper lien claimant who has a contract with someone other than the property owner and includes lower tier subcontractors, suppliers, laborers and lessors of rental equipment.

 

I. Contractor' s Lien

 

A. Basic requirements

 

The North Carolina General Statutes establish five requirements that must be met before a claimant may enforce a lien on real property:

 

 

• The claimant must perform or furnish labor or professional design or surveying services or furnish materials or rental equipment;

 

 

• The claimant must do so pursuant to a contract, express or implied;

 

 

• The contract must be with the owner of the real property;

 

 

• The contract must be for the improvement of the real property; and

 

 

• The claimant must comply with the procedural requirements of Part 1, Article 2 of Chapter 44A of the North Carolina General Statutes.

 

1. What does it mean to have a contract with the owner of real property?

 

In order to establish a lien on the improved real property, the claimant's contract must be with the owner of the property. Three conditions must be satisfied before a person is considered an owner of the property:

 

• The person must have an interest in the real property;

• The improvement must be made for that person; and

That person must have ordered the improvement to be made.

Many different people can have an interest in the improved real property. The "owner" is not necessarily the person whose name appears on the property deed. For example, a lease is an interest in real property, and a tenant can be an "owner" of the improved real property. Likewise, a person who enters into a written contract to purchase real property obtains an equitable interest in the property. If that purchaser orders an improvement to be made to the property, even before that person obtains title to the property, his interest in the property may be subject to the claimant's lien.

 

Contractors should think about protecting their lien rights from the moment contract negotiations begin with the owner. Finding out the owner's true interest in the real property is important for two reasons.   

First, a potential claimant may not be entitled to a lien at all if the person with whom the claimant is dealing does not qualify as an owner under the statute.

Second, the lien extends only to the actual interest the owner has in the improved real property. For example, if one contracts with a tenant, the claimant's lien might be limited to the value of the lease. In most situations, the owner of the real property has no obligation to pay a contractor for improvements made pursuant to a contract with the tenant of the property. If the tenant fails to pay the contractor for the work performed, the contractor's lien claim generally does not extend to the owner's interest in the real property. As a result, the contractor's lien is likely much less valuable than if the contractor had contracted directly with the property owner for the erection of the improvements made for the immediate benefit of the tenant.

A special situation occurs when the improved real property is owned jointly by a husband and wife. Property owned by a married couple is usually held in what is called a "tenancy by the entireties." In this situation, the property may not be encumbered without the consent of both parties. The interests of the husband and wife cannot be separated, or partitioned, and neither spouse owns a distinct individual interest to which a lien can attach. Most residential structures are owned by the entireties, and where the property is owned by both the husband and wife, the contractor is well advised to have both parties sign the contract.

2. What does it mean to improve the real property?

The statutory definitions of "improve" and "improvement" are quite broad:

 

"Improve" means to build, effect, alter, repair, or demolish any improvement upon, connected with, or on or beneath the surface of any real property, or to excavate, clear, grade, fill or landscape any real property, or to construct driveways and private roadways, or to furnish materials, including trees and shrubbery, for any of such purposes, or to perform any labor upon such improvements, and shall also mean and include any design or other professional or skilled services furnished by architects, engineers, land surveyors and landscape architects registered under Chapter 83A, 89A or 89C of the General Statutes, and rental of equipment directly utilized on the real property in making the improvement.

 

"Improvement" means all or any part of any building, structure, erection, alteration, demolition, excavation, clearing, grading, filling, or landscaping, including trees and shrubbery, driveways, and private roadways, on real property.

back to table of contents

B. Effective date of the lien

Liens relate to and take effect from the time labor or materials are first furnished at the site of the improvement by the person claiming the lien. The date the lien takes effect is important because it establishes the lien's priority with regard to other interests in the real property.

The general rule in North Carolina states that the mechanic's lien relates back to the first visible commencement of work on the site. A contractor's lien will also relate back to the first work performed on the site by any of the contractor/claimant's subcontractors.

 

C. Perfecting and enforcing a lien

To perfect a mechanic's lien, three things must be done:

 

• File a document, known as a Claim of Lien, with the Clerk of the Superior Court in the county where the property is located;

• Make sure the Claim of Lien contains all of the proper information; and

• Make sure the Claim of Lien is filed within 120 days (not four months) of the last day the claimant supplied labor or materials at the site.

 

 

1. Contents of the Claim of Lien

 

 

The lien statute requires the claimant to provide some specific information in the Claim of Lien. Most of this information can be obtained at the beginning of the job, and contractors should make it a regular practice to obtain such information at that time.

 

 

Claimant's name and address. Make sure this information is accurate. If the claimant operates different companies out of one office, the Claim of Lien may be invalid if the name of the claimant on the lien does not match the name of the party on the relevant contract.

Name and address of the record owner of the real property claimed to be subject to the lien at the time the claim of lien is filed. If possible, obtain this information from the owner at the beginning of the job. This information may also be obtained from the County Tax Office or Register of Deeds in the county where the property is located. As a matter of good practice, this information should be double checked shortly before the Claim of Lien is filed. Remember that the person with whom one has contracted may not be the actual record owner of the property - he may be a lessee, contract purchaser, or some other party. If the claimant's contract is with the lessee, for example, the Claim of Lien should contain the name and address of the record owner and the name and address of the lessee.

Description of the real property upon which the lien is claimed. Including the legal property description contained in the owner's deed often eliminates any dispute as to what property is subject to the lien. The statute also authorizes the use of a street address, tax lot and block number, a reference to a deed or other recorded instrument or any other description so long as it reasonably identifies the property subject to the lien.

Name and address of the person with whom claimant contracted for the furnishing of labor or materials. This information should be found in the parties' written contract.

Date upon which labor or materials were first furnished upon said property by the claimant. This is the first day the claimant performed any visible work at the site. The claimant may also use the first day of visible commencement of the work by any subcontractor hired by the claimant. It is a good practice to record this information in the job file on the first day. Be sure to include a description of exactly what was done on that day.

Date upon which labor or materials were last furnished upon said property by the claimant. This date establishes the beginning of the time limits for filing the Claim of Lien and a lawsuit to enforce the lien. The claimant has 120 days from the last day labor or materials were supplied by the claimant at the site to file the Claim of Lien.

General description of the labor performed or materials furnished and the amount claimed therefore. A general description of the labor performed or materials furnished is sufficient. It is not necessary to include an itemized list of materials or a detailed statement of labor performed.

 

back to table of contents

 

2. Time for filing

 

 

The Claim of Lien must be filed within 120 days (not four months) after the last day the claimant furnished labor or materials at the site. The claimant will likely have performed punchlist work after substantially completing its contract, but by measuring the lien filing deadline from the earlier date of substantial completion, the claimant will reduce the chance of missing the deadline for filing the Claim of Lien.

3. Amendment of the Claim of Lien

A Claim of Lien may not be amended. If an error is made in a filed Claim of Lien, and there is still time to file a new lien, the claimant may prepare and file a new Claim of Lien and cancel the old Claim of Lien.

4. Time for enforcing the Claim of Lien

Upon filing of the Claim of Lien in the proper form and in the proper time, the lien is perfected. Nevertheless, in order to recover any money by way of foreclosure of the lien and sale of the improved real property, the lien claimant must file a lawsuit to enforce the lien. The lawsuit must be commenced within 180 days of the last day the claimant furnished labor or materials at the site. The date of last work for the purpose of calculating the time for enforcing the lien is the same as the date of last work for the purpose of calculating the time for filing the Claim of Lien. (See Section I.C.2).

 

back to table of contents

D. Discharging and waiving a lien

The lien statutes provide the lien claimant with a limited number of ways to discharge a filed Claim of Lien. The lien claimant or his lawyer can personally acknowledge satisfaction of the lien debt to the clerk of court in the county where the lien was filed. The clerk of court will discharge the lien. Another method of extinguishing or discharging a filed Claim of Lien is to file an Instrument of Satisfaction of Lien Indebtedness with the clerk of court. When the clerk receives such a document, the clerk will cancel the lien.

A lien will also be discharged if a lawsuit is not commenced to enforce the lien within the required time, or if a final judgment has been rendered in favor of the owner of the improved real property.

The property owner or other interested party may discharge a Claim of Lien by depositing cash or a surety bond with the clerk of court in the county where the Claim of Lien was filed. The clerk of court will discharge a lien upon deposit with the clerk's office of cash in the amount of the lien or a surety bond in the amount of one and one-fourth times the amount of the lien. Unlike the other lien discharge methods listed above, this method of lien discharge does not completely discharge the lien. Depositing cash or a bond merely removes the lien from the improved real property. The lien is then transferred to the deposited cash or bond, which constitutes a fund out of which the lien claimant can recover his claim if successful. A project owner or general contractor may not require a contractor or subcontractor to waive lien rights as a condition of getting a contract. Provisions in a contract that require a party to waive lien rights as a condition of getting the contract are illegal and unenforceable.

A second type of lien waiver - a partial or full lien waiver given as a condition of payment during performance of the contract - is valid and enforceable.

back to table of contents

II. Subcontractor's Liens

As discussed in Section I, claimants who have a contract directly with the owner of the improved real property are entitled to a lien on the improved real property. The primary lien for project participants who do not have contracts directly with the owner is a lien on project funds. For these claimants (primarily, subcontractors), the improved real property may become subject to a lien in two particular circumstances discussed below (See Section II.B), but short of those two circumstances, subcontractors do not have a lien on the improved real property.

A. Lien on funds

The North Carolina lien statutes assume that the money paid by the owner to the contractor will filter down to all of the parties on the project. For that reason, the primary remedy afforded subcontractors is a lien on project funds. A "first tier subcontractor," that is, one having a contract directly with the contractor, has a lien on the project funds the owner owes the contractor. A "second tier subcontractor" has a lien on the project funds the contractor owes to the first tier subcontractor. A "third tier subcontractor" has a lien on the project funds the first tier subcontractor owes to the second tier subcontractor. This continues all the way down the line. Thus, a sixth tier subcontractor has a lien on the project funds the fourth tier subcontractor owes to the fifth tier subcontractor.

In addition to these direct liens on project funds, second and third tier subcontractors are granted certain lien rights possessed by subcontractors above them in the contract chain. A second tier subcontractor is subrogated to the rights the first tier subcontractor has to claim a lien on the project funds the owner owes to the contractor. Likewise, a third tier subcontractor is subrogated to the lien of the second tier subcontractor, including the second tier's right to be subrogated to the lien of the first tier subcontractor.

A subcontractor/claimant's establishment of a lien on the funds serves as notification to those above him in the contract chain that money has not been properly paid downstream. The claimant may be able to prevent the party above him in the contract chain from getting paid until the claimant's lien claim has been satisfied.

 

1. Funds subject to the lien on funds

In this discussion, we will use the example of the lien available to the first tier subcontractor, although the principles are the same for all liens on project funds by subcontractors and suppliers. A first tier subcontractor is entitled to a lien on funds that the owner owes to the contractor; and which arise out of the improvement.

If the contractor has been paid in full before the first tier subcontractor's lien on funds is perfected, this lien on funds will be ineffective because no funds are owed to the contractor upon which the lien may attach. If the contractor is performing on two different projects for the owner and has been paid in full on the project on which the first tier subcontractor has asserted lien rights, but is still owed money by the owner on the other project, the subcontractor's lien will remain ineffective. The lien will not extend to the money the owner owes the contractor on the other project. The subcontractor's lien is limited to funds arising out of the improvement on which the subcontractor worked.

 

 

2. Perfecting and enforcing a lien on funds

To obtain a lien on funds, the subcontractor sends a Notice of Claim of Lien (not to be confused with a Claim of Lien, which is document filed to perfect a lien on the improved real property) to the party who is holding the project funds owed to the person who owes the subcontractor as well as to all those parties up the contract chain who may be holding project funds to which the claimant may have rights through subrogation.

This lien on funds is perfected when the person who has the project funds receives the Notice of Claim of Lien. The statute defines this person as the "obligor." For the first tier subcontractor claimant, the owner is the obligor because the owner owes money to the contractor. For second tier subcontractors, the contractor is the obligor, because the contractor owes money to the first tier subcontractor. For third tier subcontractors, the first tier subcontractor is the obligor, because the first tier subcontractor owes money to the second tier subcontractor. Unlike the Claim of Lien, which is filed in the office of the clerk of court, the Notice of Claim of Lien is not filed.

The Notice of Claim of Lien is served upon all appropriate project participants.

 

 

 

a. Contents of the Notice of Claim of Lien

 

 

The Notice of Claim of Lien must contain the following information:

Name and address of the person claiming the lien. Be specific and accurate. The obligor may never have heard of the lien claimant and may need to contact the claimant in order to arrange payment of the claim.

A general description of the real property where labor or materials furnished. Be specific. Many obligors have several projects going at any given time. The obligor must be able to identify the project so that he can identify the project funds to which the lien must be applied.

The name and address of the person with whom the lien claimant contracted to improve the real property. Be specific. The obligor must be able to identify which one of his contractors or subcontractors has not paid the lien claimant. The obligor may need to contact that party to find out why.

The name and address of each person against or through whom subrogation rights are claimed. When a subcontractor claims rights of subrogation, each obligor up the contract chain must act upon the lien claim. If any of these parties have executed lien waivers to cut off the subrogation rights, this fact should be discovered early before the claimant spends a lot of money pursuing the claim against parties who will have a solid defense to the lien claim.

A general description of the contract and the person against whose interest the lien is claimed. A general description of the labor performed or materials furnished is sufficient along with a specific identification of the party with whom the claimant contracted.

The amount claimed by the lien claimant under his contract. Be accurate about the amount owed. Upon receipt of the Notice, the obligor is entitled to withhold from the obligee the amount claimed. If too little is claimed, the obligor is free to pay the rest and the lien claimant might never see those funds.

The claimant must send a copy of the Notice of Claim of Lien to the property owner, the contractor, and each subcontractor ahead of the lien claimant in the contract chain. The statute requires that the Notice of Claim of Lien be delivered in person or sent by certified mail. The claimant must be able to prove not only that the obligor received the Notice of Claim of Lien, but also the date the obligor received the Notice. The date of the obligor's receipt of the Notice is important because this lien becomes effective upon receipt of the Notice.

Unlike a Claim of Lien against real property, there is no time limit for serving the obligor with a Notice of Claim of Lien. The claimant merely has to serve the Notice while the obligor still owes project funds to the obligee.

 
 

back to table of contents

 

 

 

 

b. Obligor's responsibility upon receipt of Notice of Claim of Lien

If the obligor receives the Notice of Claim of Lien and owes project funds to the person who owes the claimant, the obligor must retain funds up to the amount stated in the Notice and cannot pay those funds until the claim is satisfied. If the obligor owes more money than the amount being claimed in the Notice, the obligor is only required to hold the amount that has been claimed, and the obligor is free to pay the balance owed.

If there are multiple claims to the same funds by several subcontractors and the total claimed by the subcontractors exceed the amount the obligor owes, each of the subcontractors will share the funds on a pro rata basis. Except for claims by other subcontractors, once a lien on the funds is established, the subcontractor's lien on the funds takes priority over all other claims to that money.

If the obligor receives the Notice of Claim of Lien but proceeds to pay the money anyway, the obligor may be personally liable to the claimant for the amount of money paid, up to the amount of the claim. In addition, because the claimant may have established a legal claim to the funds, the claimant may be able to sue to get that money back from the person the obligor paid.

If the obligor is the owner of the improved real property, his wrongful payment will allow the claimant to assert a lien directly against the real property.

 

c. Enforcing the lien on funds

Unlike the statutes applicable to a Claim of Lien on real property, which set forth detailed procedures for enforcing the Claim of Lien, the lien statutes set forth no specific procedure for enforcing a lien on funds.

The statute requires enforcement proceedings of a Claim of Lien to begin against the improved real property no later than 180 days after the last furnishing of labor or materials by the lien claimant. There is no specific time limit for enforcing a lien on funds.

Unless the lien claimant's demands can be worked out informally, the lien claimant will need to file suit to enforce his lien rights. In this action, the claimant sues the party who owes the claimant, the obligor and any other parties involved because of subrogation. The lien claimant will need to establish a judgment against the party who owes the lien claimant, and then petition the court for an order directing the obligor to pay the claimant out of the funds the obligor has withheld following receipt of the Notice of Claim of Lien.

 

 

3. Discharging a lien on funds

There is no statutory procedure for discharging a lien on funds. If a lawsuit has been filed to enforce the lien, dismissal of the lawsuit generally will discharge the lien. If no lawsuit is pending, the lien claimant will need to sign a lien waiver and release referencing the lien. A release of lien rights may be a good idea even if a lawsuit has been filed and dismissed.

 

 

back to table of contents

 

 

B. Lien on real property

As discussed earlier, there are two methods by which a subcontractor can claim a lien on the owner's improved real property. First, second and third tier subcontractors are subrogated to the contractor's lien rights and can assert the contractor's lien on the owner's real property if the subcontractor has served a Notice of Claim of Lien. The subcontractor also obtains a direct right to a lien on the owner's real property when the owner-obligor wrongfully pays after receiving a Notice of Claim of Lien from the subcontractor. For the most part, in utilizing either of these methods, the subcontractor must follow the same procedures as the contractor does in enforcing his Claim of Lien. There are, however, some important differences.

 

1. Contents of the Claim of Lien

A Claim of Lien filed by a subcontractor must contain the same information as a Claim of Lien filed by the contractor. If the Claim of Lien, however, is based upon wrongful payment by the owner after receiving a Notice of Claim of Lien from the subcontractor, the subcontractor's Claim of Lien must set forth the grounds the subcontractor has to believe the owner is personally liable and must have attached to it a copy of the Notice of Claim of Lien and an affidavit stating the manner in which the Notice of Claim of Lien was served on or delivered to the owner.

2. Time limits

When enforcing the Claim of Lien of the contractor by way of subrogation, the subcontractor is actually enforcing the contractor's lien. Therefore, a strong argument could be made that the Claim of Lien must be filed no later than 120 days after the last day the contractor (rather than the subcontractor) furnished labor or materials at the site. Nonetheless, the best practice is probably to obey the time limits as they apply to the claimant rather than to the contractor.

 

back to table of contents

 

 

C. Special defenses to subcontractor liens on real property - Notice of Contract

The ability of second and third tier subcontractors to assert the contractor's lien on the owners' improved real property by way of subrogation may be lost if the contractor takes certain steps.

First, the contractor must file a Notice of Contract within thirty (30) days following the issuance of the building permit for the improvement. The contractor files the Notice of Contract with the clerk of court in the county where the project is located. The contractor is also required to post the Notice of Contract in a visible location adjacent to the building permit at the project site. The Notice of Contract must contain the name and address of the contractor, the name and address of the owner of the real property, a general description of the real property, and the name and address of the person, firm or corporation filing the Notice of Contract.

The contractor's obligations may not end with the filing and posting of the Notice of Contract. Second and third tier subcontractors are entitled to demand notice of payments made by the contractor to the first tier subcontractor. Second and third tier subcontractors accomplish this by sending a Notice of Subcontract to the contractor in response to the contractor's filing and posting of the Notice of Contract.

The Notice of Subcontract is to be served personally or by certified mail. The person serving the Notice of Subcontract must be able to prove actual service. If certified mail is used, a return receipt should be requested from the post office. The Notice of Subcontract contains the name and address of the subcontractor, a general description of the real property, a general description of the subcontractor's contract, a general description of the work performed, and a request for notice of payment in accordance with the statute.

If the contractor receives a Notice of Subcontract, the contractor must notify the second or third tier subcontractor who submitted the Notice of all subsequent payments to the first tier subcontractor. The contractor must notify such subcontractor in writing no later than five (5) days following each payment made by the contractor to the first tier subcontractor following the contractor's receipt of the Notice of Subcontract. The contractor's notice of payment must include the date of the payment and the period for which payment was made. The contractor must serve the notice of payment to the subcontractor by personal delivery or by certified mail.

If the contractor files and posts the Notice of Contract, and if the contractor honors all Notices of Subcontract, the second and third tier subcontractors will no longer have the right to file a lien on the owner's improved real property through subrogation of the contractor's lien rights.

If the contractor fails to provide the notice of payment in response to a Notice of Subcontract as required by statute, the second or third tier subcontractor may enforce the contractor's lien rights and file a Claim of Lien on the real property.

 

back to table of contents

III. Forms

The following forms have been prepared using the North Carolina General Statutes as a guide. These forms may or may not be appropriate for your particular situation. These materials should not be used as a substitute for consultation with an experienced attorney. Nothing herein constitutes the rendering of legal advice.

NOTICE OF CLAIM OF LIEN BY FIRST TIER SUBCONTRACTOR

NOTICE OF CLAIM OF LIEN BY SECOND TIER SUBCONTRACTOR

NOTICE OF CLAIM OF LIEN BY THIRD TIER SUBCONTRACTOR

NOTICE OF CLAIM OF LIEN OF SUBCONTRACTOR MORE REMOTE THAN THE THIRD TIER

NOTICE OF CONTRACT

NOTICE OF SUBCONTRACT

CLAIM OF LIEN

LIEN CHECKLIST

 
 
Conner Gwyn Schenck PLLC • Construction & Surety Lawyers • Mediators • Arbitrators
 
Offices — Raleigh, North Carolina Greensboro, North Carolina